GenSystems Power Solutions, a wholly owned subsidiary of Jereh Group, has introduced PowerVEGA SST, a 3MW solid-state transformer which has been built specifically for AI data centres.

This system was revealed at the RE+ 2026 exhibition in Las Vegas, US.

Access deeper industry intelligence

Experience unmatched clarity with a single platform that combines unique data, AI, and human expertise.

Find out more

The hardware couples gas-turbine generation directly to power electronics. Operating with a 13.8kV alternating current input at 60Hz, the unit supplies an 800V direct current output with a voltage regulation accuracy within plus or minus 1%.

The platform achieves a peak conversion efficiency of 98.5%. Alongside voltage conversion, the unit integrates power distribution, uninterruptible power supply capabilities, and power quality management into a single enclosure.

It is designed to support high-density facilities as next-generation computing racks approach demands between 300kW and 500kW.

These loads challenge conventional alternating current distribution systems, while grid interconnection queues and utility capacity limits have increased interest in behind-the-metre generation.

The system also functions as a microgrid hub that manages inputs from natural gas turbines, solar photovoltaic arrays, and battery energy storage.

Additionally, it uses 2300V silicon carbide technology, which reduces overall component count by 51%. It delivers a power density of 434kW/m², or 40.4kW/ft², which the manufacturer states is 36% higher than competing systems.

The equipment measures 15.09ft by 4.92ft by 7.71ft, employs forced air cooling, and operates in ambient temperatures between 23 °F and 140 °F at elevations up to 6,562ft. Operators manage the device using a 10in colour touchscreen display.

GenSystems Power Solutions presented the transformer alongside an integrated microgrid offering that distributes energy directly from gas feedstock to the 800V DC computing environment. The manufacturer prefabricates the equipment off-site to enable eight-hour commissioning on arrival, while individual power modules feature a 300-second hot-swap replacement capability.